In an impressive accomplishment, Mammoet successfully relocated a massive dragline 27 kilometers within just ten days at the Peak Downs mine operated by BHP Mitsubishi Alliance. Weighing in at an astounding 3,100 tonnes, this giant was maneuvered using hydraulic jacks and SPMTs. A temporary ramp, completed in 72 hours for a crucial railway line crossing, helped prevent a costly three-month project delay, establishing a significant industry milestone.